Most bathroom remodels in Metro Atlanta run three to six weeks from demolition to the final walkthrough. The spread is wide because a bathroom packs plumbing, electrical, waterproofing, tile and carpentry into about forty square feet, and each of those trades has to finish before the next one can start.
What follows is the schedule we actually work to, the four things that push a project past six weeks, and how to keep a one bathroom house running while the work happens. If you are deciding whether to start before the holidays, the week by week breakdown below will tell you quickly.

A bathroom is the densest room in a house. Supply lines, drains, vents, circuits, exhaust ducting, waterproofing, tile, glass, and cabinetry all land inside a footprint smaller than most closets. Nothing happens in parallel. The tile setter cannot start until the waterproofing has cured, and the waterproofing cannot go on until the plumber has finished the rough in and the inspector has signed it off.
That dependency chain is what makes the honest range three to six weeks rather than a single number. A straight swap where the tub, toilet and vanity stay exactly where they are can finish in three. Move a wall or relocate the shower drain and you add permit review, a second inspection and usually a week of framing and plumbing that did not exist in the first version of the plan.
Everything comes out down to the studs, then plumbing and electrical get rebuilt to the new layout. This is where surprises live: old galvanized supply lines, rot under the tub, undersized venting.
The membrane goes on and has to cure before a single tile is set. Tile is slow by nature, and large format or herringbone patterns take longer to lay than a running bond.
Vanity, toilet, glass, paint, trim and hardware. Shower glass is measured after the tile is set, so it is ordered late and often sets the finish date.
This is a hall bathroom of roughly forty square feet, same layout, new everything. Treat it as the baseline and add time for the variables in the next section.
Delays are rarely random. In Metro Atlanta they come from the same four places almost every time, and three of them are decided before demolition day.
Material lead times. Tile and vanities are the usual culprits. A stocked porcelain tile ships in days, while a specialty mosaic or an imported slab can take weeks. We order and take delivery of everything before demolition starts, which is the single biggest reason a schedule holds.
Layout changes. Moving a toilet drain means opening the floor and reworking the vent. That is real framing and plumbing work, plus a permit revision and another inspection.
What the walls were hiding. Homes built around Marietta in the sixties and seventies often have cast iron drains, galvanized supply lines or a subfloor softened by a slow leak nobody saw. None of this is optional once it is exposed.
Decisions made during the job. Changing the tile after the waterproofing is on resets that part of the schedule completely. Deciding everything at the design stage is what keeps a three week bathroom at three weeks.
Note: If your house has one bathroom, say so during the estimate rather than after. We stage a single bathroom job differently: the toilet goes back into service at the end of most days, and the stretch where it genuinely cannot be used is compressed to a few days instead of spread across the project.
Shaker HazelnutView finish
Shaker Natural WoodView finish
Shaker IvywoodView finish
Oakley Sage GreenView finish
Everest Slim Shaker WhiteView finish
Oakley Tawny BrownView finish
Cambridge SableView finish
Tempo Dark WildernessView finish
Shaker HazelnutView finish
Shaker Natural WoodView finish
Shaker IvywoodView finish
Oakley Sage GreenView finish
Everest Slim Shaker WhiteView finish
Oakley Tawny BrownView finish
Cambridge SableView finish
Tempo Dark WildernessView finishWe walk the space, check what is behind the walls where we can, and give you a week by week schedule with your materials and your layout on it. Free, and no sales visit unless you ask for one.

Keystone Extreme Renovations is a licensed general contractor based in Marietta, Georgia, serving Metro Atlanta with full home renovations, kitchens, bathrooms, custom cabinets, countertops, flooring, and roofing. One source, one team, zero stress.
Premium home renovations handled by licensed professionals with 25+ years of hands-on craft. One source. One team. Zero stress.
on Google